National field manual

Review substitutions before an additive enters the tank

Compare a proposed material change against the accepted formulation, equipment, site requirements and approval responsibilities.

A substitution is a change to the planned system. It may involve a different mulch, binder, fertilizer, dye or amendment, or a different formulation sold under a familiar description. The change should be reviewed before delivery and loading. Once mixed into a tank, product identity and acceptance questions become harder to resolve, and the available options may be more limited.

Identify exactly what is changing

Record the accepted product and proposed alternative with manufacturer, full name, package form and document revision. Describe the reason for the request without treating it as technical justification. Availability, price or delivery timing may explain the proposal, but they do not establish suitability. Include whether the change affects one batch, one zone or the entire project.

Do not compare only a broad ingredient name. A preblended matrix is more than its fibre description, and a concentrated liquid is not interchangeable with a dry binder by container count. Ask the supplier to identify composition and installation differences in writing.

Compare against the accepted purpose

Use the project's requirements as the checklist: vegetation objective, erosion-control function, site limits, preparation, exposure period, environmental restrictions and acceptance evidence. A replacement may be suitable for one purpose but not another. For example, a product approved for a routine turf application has not thereby been accepted for an engineered slope treatment.

Caltrans' material categories show why fibre, tackifier, BFM and FRM should not be collapsed into one generic treatment. Its California requirements are examples of specification structure, not the approval basis for a Canadian substitution.

Review the complete formulation

Determine which additives are already included in each product and whether the proposed combination is manufacturer-supported. Adding a familiar tackifier to a replacement mulch can create a third formulation that neither supplier has documented. Do not assume that extra binder, fertilizer or soil amendment is harmless because each ingredient is sold for landscaping.

The LSC Flex Guard manufacturer page demonstrates the importance of a named system and its supporting documents. Obtain the alternative manufacturer's complete package, including technical instructions and conformance evidence relevant to the project. A sales email saying “equivalent” should be supported by a comparison.

Check equipment and process changes

Confirm compatibility with the exact machine, pump, agitation, hose and nozzle configuration. Review loading limits, mixing sequence, water requirements and application method. A product change can require a different process even when the desired treated area remains the same. Resolve conflicts between equipment and material instructions through the manufacturers.

Update the batch calculation if the accepted rate basis or packaged concentration changes. Do not preserve the old bag count simply because the crew knows it. Include the measurement method for partial quantities and the handling of any previously opened stock that will no longer be used.

Review safety and environmental implications separately

Compare SDS information, handling controls, storage incompatibilities and emergency arrangements. CCOHS describes the SDS as a hazard communication document; it is not a performance certificate. Workers need the applicable information and training before handling the new product.

Then review environmental and project restrictions through the responsible approval process. A product being non-hazardous under one classification does not establish permission for use near water or in sensitive habitat. Avoid treating a green marketing claim as a substitute for the required project acceptance.

Assign approval and preserve the decision

Name the person authorized to accept the substitution: this may involve the designer, owner, contract administrator or another defined role. The operator should not be left to resolve a specification change at the tank. Record the decision, its scope, conditions and date. If approval is refused or incomplete, keep the proposed material out of accepted stock.

Review fieldRequired comparison
Performance basisEvidence relevant to the same site purpose
InstallationRate, method, weather and equipment differences
HandlingSafety, storage and training changes
AcceptanceAuthorized decision and any conditions

Use a worked substitution request structure

A useful request might state that the accepted product cannot meet the delivery date and identify the exact proposed alternative. Attach both technical sheets, both safety documents and the relevant specification. Provide a comparison of composition, accepted use, rate basis, equipment requirements, application method, weather limits and care. Leave unsupported equivalence claims out of the request.

Then state the proposed scope: one identified zone or the whole project, the quantity, the delivery date and any effect on the schedule. Ask for a decision from the authorized reviewer, including conditions. A response that approves the product only for a limited area must remain limited in the field plan. Keep any manufacturer compatibility confirmation attached but separate from contractual acceptance.

If information is missing, list the outstanding question and who will answer it. This makes the request reviewable without forcing the recipient to reconstruct the proposal from several messages. It also prevents schedule pressure from turning an incomplete supplier suggestion into an assumed approval. Once accepted, the change needs a revised calculation and crew briefing before the first affected batch.

Schedule the review early enough that the decision can affect procurement. A request sent after the replacement is mixed into the tank no longer offers the same practical choices.

Carry the change into field records

Revise the accepted product list, batch sheet, inventory and inspection plan. Make the change visible to every affected crew member. Record which zones receive the alternative so later observations can be interpreted accurately. Preserve the earlier version rather than deleting the evidence of what was originally planned.

Continue with binder compatibility, storage controls and quantity reconciliation. A substitution is complete when both the technical decision and the revised field process are clear.

Sources and further reading

Read each source in its own product, jurisdiction and project context. Local requirements and the actual project documents govern the work.

Bring the chapter into your project

Keep the relevant measurements, documents, observations and unresolved questions together. Your enquiry brief remains editable before you choose to send it.

Prepare your project enquiry ↗

A clearer next step

Bring your questions.
Leave with a better brief.

Tell HAUSE what you are planning, what you have observed and the decision you need help with.

Start a service request